| Rittman
City Council Met in
A Special Meeting
on Monday, July 23, 2007 at 7:00 p.m.
| Members
Present: |
Faye
Telford, James Johnson, Glen Russell, |
| |
Steve
Johnson, Charles Copley |
| Members
Absent: |
Richard
Lapehn |
| Presiding: |
Mayor
William Robertson |
Council
Member Richard Lapehn arrived at 7:03 p.m.
James
moved to open the floor for public comments, no opposition
was stated and motion carried.
Workshop
Discussion with the Architects and the Proposed
Contractor Regarding the Recreation Center Roof Replacement
Jeff Day of Harris Day Architecture advised Council
received a letter of recommendation approximately 2
½ weeks ago for hiring the Knoch Corporation
and he didn’t have anything new to add, but he
and Eric Binsley, Project Manager of the Knoch Corporation,
who was the apparent low contractor, were present to
answer any questions. Day advised he spent over an hour
and half meeting with Eric and his people and the roofing
subcontractors to go over the details of the drawings
and specifications to make sure they had everything
covered. Day advised the Knoch Corporation was anxious
and ready to move ahead and have assured him that everything
there were concerns about were included in their bid.
Day advised as indicated in his letter, they have worked
with the Knoch Corporation for over 25-30 years and
they have just completed a roofing project over a natatorium
with the same roofing system specified for this project
so, they know Knoch Corp. has familiarity with the system
and the installation requirements being requested. Day
advised as a part of the Harris/Day contract with the
City, in conjunction with the roofing consultants RoofTec,
one of their people must be onsite everyday during construction
to make certain contractors and roofing subcontractors
are adhering to their specifications and drawings and
should anything arise that is unclear or questionable
his office would be immediately notified. He advised
they also have a requirement from the roofing manufacturer
to have a representative present at the site once a
week. Day advised they have some good checks and balances
in place and they feel they have a good team and it
was a complicated project and it was understandable
if there were questions.
Council Member Steve Johnson inquired as to how many
days they anticipated the project to take (until complete).
Day advised if they receive approval tonight, they anticipate
within two weeks they would be able to mobilize and
have their pre-construction meeting. He advised they
have allowed a two-month variable, which takes them
to the end of October although they expect to be done
by the early part of October.
Council Member Charles Copley inquired as to whether
or not during construction there would be a point where
the entire center would need to be closed.
Day advised no, although they may have to temporarily
close the front entrance and they have discussed this
with the Recreation Director and can arrange for alternate
points of entry during that time as part of the natatorium
roof ties into the main entrance. He advised most of
the work was going to be over the natatorium, which
has already been closed down for well over a year.
Copley inquired as to what was involved in color matching
the old roof and if it affects the roofing material
to be dyed.
Day advised it didn’t and they have had conversations
with the roofing manufacturer who will use a sample
to color match and it was the same process for a standard
color as it was for a special color.
Steve inquired regarding the work in the foyer and the
problems with that ceiling discoloring and the moisture
if it was related to the other problems.
Day advised it was directly related and the area from
the pool roof to the foyer was a direct line of movement
and vapor and moisture and the new roofing system would
take care of that and why they have to do both (areas)
as well as for aesthetics. Day advised there was an
allowance in the specifications to allow for cleaning,
painting and repair of the inside unless they run into
something more than what was visible.
Steve inquired if the end of October date meant finished
with construction, cleaned up and ready to swim in the
pool.
Day advised yes, and he anticipated them being done
with the roofing before that time. He advised once the
roofing was complete and they were weather tight, there
was extensive cleanup on the inside as they were repainting
all surfaces and it should look like the day it was
opened several years ago.
Tom Leatherman of DeCourcey Road who is an employee
of the recreation center advised they recently painted
the surface of the pool itself and inquired as to what
would be used to protect that surface.
Day advised as a part of the protection package, plywood
would cover the entire pool deck and would be completely
protected.
Council Member James Johnson advised he understands
Knoch Corporation has experience with roofing, but inquired
as to their track record with re-construction of roof
projects.
Eric Binsley, Project Manager of Knoch Corporation advised
he didn’t have those figures off the top of his
head, but he could provide those for Council if they
wished.
James inquired if during demolition they find damage
in the walls, was there an allowance in the bid for
fixing wall damage.
Day advised the specifications do not address the walls
and if they would identify something they would bring
it to Council’s attention and address it at that
point in time.
Copley advised he felt basically they were re-doing
the roof because they had a roof that didn’t last
and he inquired as to what type of guarantee would be
provided for this roof and what was his experience with
this material.
Day advised this roof material was a membrane that the
roof consultant spent a lot of time researching and
it was a new generation product, but it does carry a
20-year warranty plus 2 year 100% labor warranty on
the general contractor to follow through on his end.
Day advised regarding the question of re-construction,
really it was the same as putting a new roof on as they
were going down to the structural steel and rebuilding
another roof deck, new substrate, new vapor barrier
and a new roof system so in a lot of ways it was just
like a new roof.
Discussion continued regarding Sarnafil, the roof manufacturer,
who was the same manufacturer used on the new Rittman
Elementary School.
Rick Hanlon of Olds Avenue inquired if there was a penalty
phase if the roof was not completed by the end of October
and if so, how many rain delay days were there (included
with the specifications).
Day advised yes, there were liquidated damages and he
estimated it was approximately $500. a day over the
completion date and there were provisions for rain delays.
He advised they would document every one of those working
days with their on-site member of staff.
James inquired as to the life of the color of the roof
since it does have to be dyed.
Day advised he couldn’t speak to that issue directly,
but whether it was a standard color or a specially matched
color, the fading was going to be the same.
Shawn Vallery of Joshua Drive advised she believed the
original roof was shown to be defective and inquired
if it was shown to be attributable to the design, the
material or the workmanship.
She was informed that question was directly related
to the litigation and the City had to be very careful
with their response.
Vallery advised she understood, but inquired if it had
been determined as to what it was attributable to.
City Manager Boggs advised there have been reports,
but those were being argued in litigation and whether
or not those findings were determined to be factual,
he couldn’t say.
Vallery inquired if it was not known precisely what
the cause or failure was originally, how could a company
determine that their roof would be fail proof and withstand
whatever made the original roof fail.
Mayor Robertson advised it appeared from what he saw
in the reports that the rusting came from the inside
out and there was moisture between the tectum roof and
the steel roof deck that caused the steel to rust. He
indicated they would be using PVC material for the new
roof structure and it wouldn’t rust. Robertson
advised it was a different material and there would
be a more comprehensive vapor barrier to keep the moisture
out, as there should never have been moisture between
those layers. Robertson advised in litigation they were
trying to determine what part in the whole process was
missed and allowed the moisture to enter. He advised
obviously chlorine water causes the rusting to happen
faster and cause more damage.
Vallery inquired if this new roof was preventing something
by varying the materials as well as the workmanship
was going to be very different from what was originally
done.
The Mayor advised yes, although the original design
of the tectum roof and the metal roof deck has been
successful in natatorium design. He advised this was
a completely different approach to the situation.
Vallery inquired as the roof gets dismantled, if there
would be documentation as to what (caused the problem).
Robertson advised all parties in the litigation have
taken documentation as well as sections of the roof
will be saved for evidence. Robertson advised they needed
to be real careful as it was still in the process of
litigation.
Vallery advised she appreciated his explanation, as
she didn’t understand if no one was familiar with
the cause of the problem, how could they repair it,
but apparently there is some understanding of what most
likely caused the problem.
Day advised he had a stack of manuals that talk about
what they think is up there (in the roof), plus his
own professional background and they have addressed
it in a way they feel will be satisfactory. Day advised
with regards to the warranty, if there was going to
be a problem, it would show up within the first two
years and the reason for the extra burden on the general
contractor in addition to the roof warranty and it was
pretty standard in their specifications.
James inquired if during the demolition phase the ductwork
for heating and the airflow system inside the pool area
would be stripped out and if so, would they install
all new or recycle the old.
Day advised the ductwork remains and would be protected
to the degree possible. He advised light fixtures would
be covered and protected and everything would get scraped
clean and painted. Day advised they felt the ductwork
could stay in place because it was suspended off the
structural steel and wouldn’t be affected. Day
advised the roof was made up of tectum planks, which
should come up in sections and they were anticipating
a fairly smooth take-off (of the roof) although there
would be dust and debris.
Carl Jentes of Lane Street inquired if you state the
problems with the roof show up in the first couple of
years, didn’t 4 or 5 years pass before they discovered
this current problem.
Steve advised they discovered problems right away.
Mayor Robertson thanked all for their questions and
concerns.
Old
Business
a. Ord. No. 7452 An Ordinance of the Council
of the City of Rittman, Ohio, Wayne and Medina Counties,
Authorizing the Municipal Manager to Enter Into a Contract
with the Knoch Corporation of Canton, Ohio for the Roof
Replacement and Repairs for the Recreation Center and
Declaring an Emergency. Second and Third Reading. Ord.
No. 7452 was read on second reading. James moved to
suspend the rules and have third reading, all Yeas on
roll call and motion carried. Ord.
No. 7452 was read on third reading. Telford moved to
adopt, all Yeas on roll call and motion carried.
Motion to Adjourn – 7:23 p.m.
Russell so moved, all Yeas on roll call and motion
carried.
|